Creative landscaping with the charcoal color block from Sholin. The charcoal block blends perfectly into a shaded areas.
Steps were installed to gain access to the different platform levels by means of turning the CK1 kerb, manufatured by Mobicast, upside down. The filling below the steps were stabillised with cement and compacted by rammer.
A concrete footing of 700mm X 200mm @ 15mpa were cast for the entire wall and a subsoil drain was installed behind the bottom tier. All filling have been compacted by rammer in layers of 160mm. The blocks were filled with hand tamped topsoil.